This procedure outlines the Department of Education’s (the department) approach to developing effective policies and procedures consistent with the Policy management framework.

Overview

Policies and procedures allow the department to articulate its functions, responsibilities and purpose, while also managing operational issues and risks. Policies provide the overarching intent, imperative or direction for departmental activities. Procedures set out what the department and its staff will do, and how those activities will be carried out.

Responsibilities

Content authors

  • prepare and submit Initiation proposals, including exemption requests if required
  • develop and review policies and procedures in line with the Policy management framework’s development and improvement cycle and Checklist
  • consider human rights when developing or reviewing policies and procedures and ensure requirements and proposed actions are compatible with the Human Rights Act 2019 (Qld), where applicable
  • consult with all relevant stakeholders to ensure policies and procedures are fit for purpose
  • seek appropriate approval for changes to policies and procedures in line with the Implement guide and the Nominated approver schedule
  • communicate to relevant stakeholders when policies and procedures have been published or decommissioned
  • provide ongoing monitoring to ensure policies and procedures remain accurate, relevant and fit for purpose.

Consultation stakeholders (internal and external)

  • review policies and procedures circulated for consultation and provide feedback to content authors.

Policy and Procedure Register team (PPR team), Strategy and Performance 

  • provide advice and support to content authors and owners on the development and management of policies and procedures
  • progress Initiation proposals and exemption requests to the Executive Leadership Team (ELT) for approval
  • maintain an ELT approved Publishing schedule of policies and procedures
  • manage the external stakeholder consultation process for all policies and procedures
  • ensure content meets publishing requirements and standards
  • undertake system administration activities and maintenance of departmental records for the PPR
  • monitor, review and provide management information and data to senior executives and content owners.

Deputy Directors-General (DDG) – as the content owners

  • ensure policies convey government intent and obligations, and procedures clearly outline the process and responsibilities required to support policy implementation
  • ensure policies and procedures remain current, accurate and fit for purpose
  • manage and approve policies, procedures and supporting documents, including decommissioning or transferring content ownership
  • approve Initiation proposals, including exemption requests
  • nominate appropriate approver(s) for each new policy and procedure

Deputy Director-General (DDG), State Schools Strategy

  • approve urgent exemptions to the external consultation and upcoming publishing requirements for policies and procedures related to state schooling.

Assistant Directors-General (ADG), Executive Directors or Directors – as nominated approvers

  • manage or approve policies and procedures assigned to them by the content owner
  • support content owners by ensuring policies and procedures are accurate and not overdue for review.

Executive Leadership Team (ELT)

  • provide strategic oversight for the development and management of policies and procedures
  • approve Initiation proposals and exemption requests that impact state schools
  • approve the publication timing of policies and procedures through the Publishing schedule.

Process

Policy and procedure management follows the development and improvement cycle outlined in the Policy management framework. The Policy and procedure development checklist provides a high level outline of the steps below, with more detailed guidance available in the Initiate, Author, Consult, Approve, Implement and Manage guides.

Image 1 – Policy and procedure development and improvement cycle

Initiate

Identify the type and scope of work required

  • The content owner or author identifies the:
    • need for a new policy or procedure, or changes to an existing one. Refer to the Policy management framework and Threshold considerations to determine the most suitable policy instrument and hierarchy to meet business objectives.
    • key process requirements based on the type of work and the school impact, as per the below table.

Type of work

Impact on state schools

Key process requirements

New policy or procedure, full review, or major update

Yes

Complete the full process in this procedure, including Part A of the Initiation proposal for ELT consideration, consultation, approval and publishing requirements.

New policy or procedure, full review, or major update

No

Complete Part A of the Initiation proposal for content owner endorsement. Progress through the full process, noting that ELT consideration, PPR-led external consultation and publishing as upcoming are not required.

Minor update to existing content

Yes or No

Request the master copy from the PPR team, make updates using track changes, obtain approval from the nominated approver at CM 20/519237 (DoE employees only), and provide the updated documents and approval record to the PPR team for publishing.

Review date reset

Yes

Complete Part B of the Initiation proposal, request the master copy of the policy or procedure from the PPR team, make any required minor updates using track changes, obtain DDG approval, and provide the documents to the PPR team. The PPR team can publish the updated content following ELT approval of the review date reset.

Review date reset

No

Complete Part B of the Initiation proposal, request the master copy of the policy or procedure from the PPR team, make any required minor updates using track changes, obtain DDG approval, and provide the documents to the PPR team for publishing.

Decommission existing policy or procedure

Yes

Complete Part A of the Initiation proposal. Consultation is required where requested by the content owner or otherwise considered necessary. The PPR team will progress the proposal to ELT and, following approval, implement the decommissioning.

Decommission existing policy or procedure

No

Complete Part A of the initiation proposal. Consultation is required where requested by the content owner or otherwise considered necessary. The PPR team can decommission the content following receipt of a DDG approved Initiation proposal.

Transfer of content ownership

Yes or No

Prepare a DDG briefing note for consideration and approval by the transferring and receiving content owners. The PPR team can transfer content ownership on the PPR to the new owner following receipt of the approved DDG brief.

Content author seeks content owner endorsement

  • Where an Initiation proposal is required, the content author must:
    • prepare the Initiation proposal, completing either Part A or Part B, to articulate the intent of the planned work for senior leaders. Refer to the Initiate guide (DoE employees only) for further information about Initiation proposals.
    • include any requests for exemption from external consultation or publishing as upcoming requirements. Exemptions are expected to be rare and must include clear reasons. Exemptions are not required for policies and procedures that do not impact schools.
    • submit the Initiation proposal, and any draft documents required for Part B proposals, to the content owner for endorsement.
    • provide the Initiation proposal and content owner endorsement to the PPR team via email or by providing a Content Manager (CM) location.
  • Where proposing to transfer ownership of a policy or procedure, the content author must:
    • prepare a DDG briefing note outlining the proposed action and supporting rationale.
    • obtain approval from the relevant DDG as the content owner and the incoming content owner.
    • provide the approved briefing note, and any supporting documents, to the PPR team via email or by providing a CM location.

PPR team progresses and actions requests

  • The PPR team reviews the documentation provided by the content author and confirms the next steps:
    • for matters that require ELT consideration, the PPR team submits key information from Initiation proposals, including any exemption requests, to the ELT each month for consideration.
    • for matters that do not require ELT consideration, the PPR team actions the request on receipt of the approved documentation, including implementing approved review date resets, decommissioning content or updating ownership records.

ELT considers and decides on planned activities

  • The ELT considers and either approves or declines Initiation proposals and any exemption requests.
  • The PPR team records the ELT's decision and advises the content author.
  • The PPR team saves Initiation proposals in CM location 360/1/131-0003 (DoE employees only) to provide visibility of upcoming work across the department.
  • For approved Initiation proposals that take immediate effect, including a review date reset or the decommissioning of a policy or procedure, the PPR team implements the approved changes.

Author

Content author develops or reviews content

  • The content author drafts content in the approved policy or procedure template, ensuring that:
    • master copy documents for existing policies, procedures and supporting documents are requested from the PPR team
    • the policy or procedure clearly identifies all minimum mandatory requirements, who is responsible, and the activities that must be undertaken. Resources to guide drafting of content are available on the PPR OnePortal page (DoE employees only).
    • requirements relating to child safe organisations (DoE employees only) and students with disability (DoE employees only) are considered and addressed where required.
    • human rights are considered, including whether any decisions or actions may engage human rights. Where human rights are engaged, ensure the policy or procedure includes appropriate requirements for decision makers/action officers to consider human rights and make decisions/actions that are compatible with the Human Rights Act 2019 (Qld).
    • content is drafted in plain English, meets publishing requirements, and follows the language and formatting conventions outlined in the Author guide (DoE employees only).

Consult

Undertake stakeholder consultation

  • The content author ensures draft policies, procedures and supporting information are provided to all relevant internal and external stakeholders during the drafting process.

Internal consultation

  • Internal consultation is managed by the content author.
  • Prior to content approvals, the content author provides draft content to the PPR team for quality assurance, advice on alignment with the Policy management framework, and review against publishing standards.
  • The PPR team reviews the policy or procedure and any supporting documents, and provides feedback to the content author for consideration.

External consultation

  • External consultation during the development or drafting stage is managed by the content author.
  • External consultation on the proposed final document is facilitated by the PPR team. Refer to the Consult guide (DoE employees only) for more information, including timeframes.
  • PPR-led external consultation is required if the policy or procedure:
    • impacts state schools or school staff; and
    • is new, has undergone a full review (unless a review date reset has been approved), or has undergone major updates that affect stakeholders or staff. 
  • The content author must prepare the policy, procedure, any supporting documents and a Summary of changes template (DoE employees only) for external consultation and obtain Executive Director approval to release the documents.
  • If an exemption from PPR-led external consultation is required, approval must be obtained from the content owner and the ELT through the Initiation proposal or, in urgent situations, from the content owner and the DDG, State Schools Strategy.

Finalise draft

  • The content author incorporates relevant stakeholder and PPR feedback and finalises the draft policy and/or procedure and any supporting documents.

Approve

Approve publication timing

  • The content author confirms the upcoming publication timeframe with the PPR team.
  • The PPR team records publication information in the Publishing schedule and provides this to the ELT on a quarterly basis.
  • The ELT considers upcoming publishing activity, including its potential impact on state schools and school staff, and approves or declines the proposed publishing timeframes in the Publishing schedule.   

Approve content for publication

  • The content author progresses the draft policy or procedure, any supporting documents, and an updated Summary of changes template (DoE employees only) for approval:
    • The content author must refer to the Approve guide (which explains different types of changes) and the Nominated approver schedule (CM 20/519237, DoE employees only), to determine the appropriate approver. 
    • To obtain approval, the content author can use the Deputy Director-General briefing note template (DoE employees only) or, for minor and major updates, provide a record of approval via email or CM.
    • The content author must seek clear decisions/approvals from the content owner or nominated approver about:
      • the proposed action for each document, including clear advice about whether documents are being updated, introduced as new documents, transferred or otherwise amended
      • nominated approvers for the policy or procedure, if the content is new or a change to existing nominated approvers is recommended
      • the results of consultation and how feedback has been addressed, including consultation with the PPR team and other stakeholders
      • publishing timeframes, including whether the policy or procedure will first be published as upcoming before becoming effective at a later date, or if an exemption is needed because there is a critical need for the content to become effective immediately. For more information about publishing timeframes, refer to the Implement guide (DoE employees only).
  • The content owner or nominated approver will consider the approval request and decide whether to approve publication of the policy or procedure, supporting documents and the Summary of changes template (DoE employees only).
  • By approving content for publication on the PPR, the content owner or nominated approver confirms that the content is accurate, relevant human rights considerations have been addressed and content meets departmental requirements and standards.

Implement

Publish or decommission policy or procedure 

  • The content author provides the approved policy or procedure, Summary of changes and any supporting documents to the PPR team for publication on, or decommissioning from, the PPR. Publishing timeframes are outlined on OnePortal (DoE Employees only).
  • The PPR team ensures the documents meet departmental publication standards and requirements (DoE employees only) and publishes the content to the PPR as upcoming or effective, in accordance with the approvals.
  • The PPR team maintains records of all PPR publication and decommissioning activities in the department’s record management system following the department’s Records management procedure.

Communicate policy or procedure to stakeholders

  • The content author should advise key stakeholders that the policy or procedure has been published or decommissioned. Refer to the Implement guide (DoE employees only) for further information about communication. 
  • The content author must advise the PPR team of the approved transfer of a policy or procedure so departmental records can be updated.
  • The PPR team invites content authors to present at information sessions for regional staff to help prepare them for upcoming changes to policies and procedures.

Manage

Monitor and review policies and procedures

  • Content owners must ensure their policies, procedures and supporting documents are monitored and periodically reviewed using the development and improvement cycle. Refer to the Manage guide (DoE employees only) for further information about monitoring and review, including how to conduct full reviews, make minor or major updates, request a review date reset, or decommission a document from the PPR:
    • Policies are to be fully reviewed at least every five years, and procedures at least every three years. Supporting documents should be reviewed at the same time as their overarching policy or procedure.
    • Reviews must be holistic and critically examine all content to ensure accuracy, relevance, clarity and reliability. Reviews should also seek and consider feedback from key stakeholders and end users.
    • The review date on the published policy or procedure can only be updated when:
      • a full review process has been undertaken, meaning the content has been holistically reviewed for currency and quality, rather than updated through ad hoc changes or corrections, or
      • the content remains current and a review date reset has been approved through Part B of the Initiation proposal. Note that the review date cannot be reset for two consecutive review cycles.
  • If a policy or procedure is no longer required, the content author may propose its decommissioning and removal from the PPR through Part A of the Initiation proposal.

Definitions

Term

Definition

Content owner

A member of the department's Executive Leadership Team, usually the DDG of a division, who is accountable for the policies, procedures and supporting documents owned by that division. While the responsibility for updating and implementing policies and procedures may involve several divisions, there can only be one content owner to ensure clear accountability for policy management.

Decommissioned policy or procedure

A policy or procedure that is no longer applicable and is removed from the Policy and Procedure Register.

Effective date

The date on which a document comes into force. "Published as effective" means the document comes into force as soon as it is published, rather than being published as upcoming. Documents that are new, fully reviewed or have had major updates generally become effective on the first day of a school term.

Full review

A comprehensive evaluation of a policy or procedure and its supporting documents to ensure accuracy, clarity, consistency, and alignment with organisational requirements. It involves assessing and redrafting content, as well as completing mandatory steps such as consultation, quality assurance, and approvals.

Impact on state schools

The extent to which a policy, procedure or supporting document applies to state schools or affects the responsibilities, requirements, processes or operations of principals, teachers, school staff or school communities.

Major update

A change to an existing policy or procedure that materially alters its intent, scope, requirements, responsibilities, process, or impact on staff, schools or other stakeholders.

Examples include mandating the use of a new system, introducing or removing duties for staff, altering the existing process or approach, or making changes to content that is contentious or likely to attract media attention.

Minor update

A change to an existing policy or procedure that does not materially alter its intent, scope, requirements, responsibilities, process or impact on staff, schools or other stakeholders. A minor update is administrative, corrective or low risk in nature.

Examples include updating hyperlinks and contact details, correcting typos or clarifying the wording without altering the existing process.

Nominated approver

The position nominated by the content owner to approve changes to policies and procedures on their behalf as per the Publish guide.

Policy

A policy:

  • provides government direction and purpose
  • establishes a clear and concise statement of the department’s intent, actions and requirements.

Compliance with a policy is mandatory.

Policies are drafted in the approved departmental policy template and published on the Policy and Procedure Register.

Procedure

A procedure:

  • provides the ‘how to’ and sets out processes to implement the policy
  • identifies responsibilities for individuals or business areas
  • cannot override or conflict with policies. 

Compliance with a procedure is mandatory.

Procedures are drafted in the approved departmental procedure template and published on the Policy and Procedure Register.

Policy management framework

The department’s framework for initiating, developing, implementing, communicating, monitoring and reviewing policies and procedures.

Policy and Procedure Register (PPR)

The department's central source of truth for operational policies and procedures. The PPR is publicly accessible at ppr.qed.qld.gov.au.

Review date reset

An approved extension of the review date of an existing policy or procedure where a full review is due but the content is still current.

Supporting documents

Documents that provide advice, guidance or tools to support staff to comply with the department’s policies and procedures.

Examples include, but are not limited to, guidelines, checklists, information sheets, frequently asked questions, forms, notices, sample legal agreements and sample letters.

Upcoming

A publication status for policies and procedures on the PPR indicating that the content is accessible but not yet in force until the effective date. Policies and procedures that are new, fully reviewed or have had major updates are generally published as upcoming for at least the last four weeks of school term prior to the effective date. Publishing content as upcoming enables schools and stakeholders to prepare for implementation before the content takes effect.

Legislation

Delegations/Authorisations

  • Nil

Other resources

Policy management

Related policies, procedures and frameworks

Superseded versions

Previous seven years shown. Minor version updates not included.

2.0 Policy and procedure development and improvement cycle procedure

Review date

11 November 2029
Attribution CC BY

Policies and procedures in this group

  • Policy and procedure development and improvement cycle procedure (current page)
SocialMedia_BottomRight